Luke Moger, PMP, Operations Manager, gave an update on the Mount Polley mine site at the CIM Vancouver Branch October Luncheon.

 

The presentation focused on the period since the 4 August 2014 foundational failure (and resulting breach) occurring at the mine’s Tailings Storage Facility (TSF), describing the transition from emergency response and repair of the TSF through to the return to full operations in 2016. Updates on TSF breach remediation, site water management and operations were provided, as well as an overview of future plans for the site.